Implementation of the third pellet plant, comprising the construction of a new beneficiation unity at Germano, MG, a pelletizing plant at Ponta Ubu, ES, and the second pipeline for ore slurry (396 km), linking these unities and passing through 25 cities in two States.
The objective is to increment the pellets production from 14 Mtpy to 21 Mtpy.
Main quantities:
- 98.000 m3 of concrete
- 4.000.000 m3 of earthmoving (including excavation)
- Around 13,000 ton of steel structure
- Around 22,000 ton of equipment
Project period: January 2005 to May 2008
Total investment: US$ 1,183 billion, being US$ 279 million at Germano; US$ 299 million for the pipeline; and US$ 605 million at Ponta Ubu.
Logos scope: Overall Project Management
- Elaboration of the Project Execution Plan
- Time and cost planning and control
- Support to engineering activities (contracts administration, documenting and interfaces coordination)
- Support to procurement activities (contracts administration and closure, supply and interfaces coordination)
- Construction Management, including contracts administration and logistics coordination